Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-158-12-47 10-1H8904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-SJ-4-14.8/14.8 NONE Progress payment No. 004 Payment period ending: 05-16-18 NEUDECK CONCRETE RESTORATION INC 3816 E DON PEDRO RD CERES CA 95307 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 353,948.14 52,320.18 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 353,948.14 52,320.18 5. Mobilization 6. Total Work Completed 353,948.14 7. Deductions -20,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 333,948.14 32,320.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 32,320.18