Dept. of Trans. PROGRESS Serial No. Contract No. 22-083-14-22 10-1J3004 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 86% Location: Federal Project: 10-MER-152-21.0 SSTG-S152(92) Progress payment No. 007 Payment period ending: 03-20-22 AGEE CONSTRUCTION CORPORATION PO BOX 629 CLOVIS CA 93613 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 787,305.61 0.00 2. a. Extra Work 23,653.62 17,728.26 b. Adustment Comp. 33,280.74 6,498.51 3. Materials on Hand 4. Earned Subject to Retention 844,239.97 24,226.77 5. Mobilization 28,000.50 0.00 6. Total Work Completed 872,240.47 7. Deductions -10,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 862,240.47 34,226.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,226.77