Dept. of Trans. PROGRESS Serial No. Contract No. 22-263-10-26 10-1J5304 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 18% Location: Federal Project: 10-SJ-4-0.0 NONE 10-SJ-5-0.0 10-SJ-120-0.0 Progress payment No. 002 Payment period ending: 09-20-22 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 219,755.64 192,208.37 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 219,755.64 192,208.37 5. Mobilization 165,000.00 165,000.00 6. Total Work Completed 384,755.64 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 384,755.64 357,208.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 357,208.37