Dept. of Trans. PROGRESS Serial No. Contract No. 22-332-16-27 10-1J7804 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 33% Location: Federal Project: 10-SJ-99-24.5/24.5 SSTG-000C(534) Progress payment No. 002 Payment period ending: 11-20-22 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 248,357.45 134,616.75 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 85,000.00 85,000.00 4. Earned Subject to Retention 333,357.45 219,616.75 5. Mobilization 76,845.50 16,178.00 6. Total Work Completed 325,202.95 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 410,202.95 235,794.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 235,794.75