Dept. of Trans. PROGRESS Serial No. Contract No. 21-327-14-08 10-1L1204 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 41% Location: Federal Project: 10-MER-152-15.1/15.6 NONE Progress payment No. 004 Payment period ending: 11-20-21 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 556,099.90 30,429.40 2. a. Extra Work 1,320.00 1,320.00 b. Adustment Comp. -5,002.78 -5,002.78 3. Materials on Hand 4. Earned Subject to Retention 552,417.12 26,746.62 5. Mobilization 146,300.00 0.00 6. Total Work Completed 698,717.12 7. Deductions 0.00 3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 698,717.12 29,746.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,746.62