Dept. of Trans. PROGRESS Serial No. Contract No. 22-026-07-04 10-1L1204 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 58% Location: Federal Project: 10-MER-152-15.1/15.6 NONE Progress payment No. 006 Payment period ending: 01-20-22 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 990,846.63 242,300.73 2. a. Extra Work 21,063.50 0.00 b. Adustment Comp. -5,002.78 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,006,907.35 242,300.73 5. Mobilization 154,000.00 7,700.00 6. Total Work Completed 1,160,907.35 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,150,907.35 240,000.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 240,000.73