Dept. of Trans. PROGRESS Serial No. Contract No. 22-082-13-30 10-1L1204 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 77% Location: Federal Project: 10-MER-152-15.1/15.6 NONE Progress payment No. 008 Payment period ending: 03-20-22 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,466,682.73 209,052.60 2. a. Extra Work 47,917.70 0.00 b. Adustment Comp. -5,002.78 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,509,597.65 209,052.60 5. Mobilization 154,000.00 0.00 6. Total Work Completed 1,663,597.65 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,658,597.65 204,052.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 204,052.60