Dept. of Trans. SEMI-FINAL Serial No. Contract No. 25-321-13-47 10-1L1804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-SJ-132-0.3 NONE Progress payment No. 006 Payment period ending: 08-20-25 TRACY GRADING & PAVING INC PO BOX 444 TRACY CA 95378 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 849,945.00 0.00 2. a. Extra Work 154,515.57 154,515.57 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,004,460.57 154,515.57 5. Mobilization 95,000.00 0.00 6. Total Work Completed 1,099,460.57 7. Deductions -10,915.10 9,084.90 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,088,545.47 163,600.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 163,600.47