Dept. of Trans. PROGRESS Serial No. Contract No. 24-235-14-02 10-1L2604 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 100% Location: Federal Project: 10-SJ-120-R1.1/T6.6 SNHG-P120(64) Progress payment No. 003 Payment period ending: 08-20-24 PACIFIC INFRASTRUCTURE CONSTRUCTION LLC 871 COTTING CT #A VACAVILLE CA 95688 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,650,882.52 1,170,297.35 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -487,755.00 4. Earned Subject to Retention 1,650,882.52 682,542.35 5. Mobilization 220,000.00 11,000.00 6. Total Work Completed 1,870,882.52 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -117,029.74 -68,254.24 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,753,852.78 625,288.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 625,288.11