Dept. of Trans. PROGRESS Serial No. Contract No. 24-023-14-29 10-1L3304 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 90% Location: Federal Project: 10-MER-165-33.2/33.2 HSST-P165(116) Progress payment No. 005 Payment period ending: 01-20-24 ST FRANCIS ELECTRIC LLC PO BOX 2057 SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 460,768.90 0.00 2. a. Extra Work 34,546.20 11,955.97 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 495,315.10 11,955.97 5. Mobilization 6. Total Work Completed 495,315.10 7. Deductions -10,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 485,315.10 21,955.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,955.97