Dept. of Trans. SEMI-FINAL Serial No. Contract No. 25-197-10-30 10-1M0504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-MPA-49-1.8/6.3 NONE Progress payment No. 004 Payment period ending: 05-27-25 CAL VALLEY CONSTRUCTION INC 5125 N. GATES AVE #102 FRESNO CA 93722 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 713,199.00 0.00 2. a. Extra Work 38,515.07 23,035.85 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 751,714.07 23,035.85 5. Mobilization 6. Total Work Completed 751,714.07 7. Deductions -130,000.00 -16,399.60 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 621,714.07 6,636.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,636.25