Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 24-025-15-04 10-1N3104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-SJ-120-16.7/17.9 NONE Progress payment No. 008 Payment period ending: 12-26-23 R E MASON ENGINEERING INC 1195 WEST SHAW AVE #D FRESNO CA 93711 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,880,837.14 0.00 2. a. Extra Work b. Adustment Comp. -23,499.16 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,857,337.98 0.00 5. Mobilization 180,000.00 0.00 6. Total Work Completed 2,037,337.98 7. Deductions -24,317.25 -6,984.75 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,013,020.73 -6,984.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -6,984.75