Dept. of Trans. FINAL Serial No. Contract No. 24-138-14-29 10-1N3104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-SJ-120-16.7/17.9 NONE Progress payment No. 011 Payment period ending: 12-26-23 R E MASON ENGINEERING INC 1195 WEST SHAW AVE #D FRESNO CA 93711 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,933,837.08 0.00 2. a. Extra Work 362,900.38 87,866.81 b. Adustment Comp. -23,499.16 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,273,238.30 87,866.81 5. Mobilization 180,000.00 0.00 6. Total Work Completed 2,453,238.30 7. Deductions -4,317.25 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,448,921.05 97,866.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 97,866.81