Dept. of Trans. PROGRESS Serial No. Contract No. 24-295-17-08 10-1N4204 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 41% Location: Federal Project: 10-VAR NONE Progress payment No. 001 Payment period ending: 10-20-24 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 246,837.33 246,837.33 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 246,837.33 246,837.33 5. Mobilization 190,500.00 190,500.00 6. Total Work Completed 437,337.33 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 437,337.33 437,337.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 437,337.33