Dept. of Trans. PROGRESS Serial No. Contract No. 25-023-15-42 10-1N4204 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 86% Location: Federal Project: 10-VAR NONE Progress payment No. 004 Payment period ending: 01-20-25 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,922,676.35 90,000.00 2. a. Extra Work 65,245.00 15,245.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,987,921.35 105,245.00 5. Mobilization 254,000.00 0.00 6. Total Work Completed 2,241,921.35 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,231,921.35 95,245.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 95,245.00