Dept. of Trans. PROGRESS Serial No. Contract No. 23-171-10-23 10-1N4304 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 45% Location: Federal Project: 10-MER-5-0.0 NONE 10-MER-152-0.0 Progress payment No. 003 Payment period ending: 06-20-23 VELARDE CONCRETE CONSTRUCTION INC 523 S. BRAND BLVD, #201 SAN FERNANDO CA 91340 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 496,026.76 445,167.54 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 496,026.76 445,167.54 5. Mobilization 232,469.75 232,469.75 6. Total Work Completed 728,496.51 7. Deductions -105,811.60 -105,811.60 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 622,684.91 571,825.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 571,825.69