Dept. of Trans. PROGRESS Serial No. Contract No. 22-332-16-41 10-1N6004 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 39% Location: Federal Project: 10-MER-99-16.3/16.4 NONE Progress payment No. 004 Payment period ending: 11-18-22 SINCLAIR GENERAL ENGINEERING CONSTRUCTION, INC. PO BOX 1453 OAKDALE CA 95361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 944,762.01 405,952.81 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 944,762.01 405,952.81 5. Mobilization 6. Total Work Completed 944,762.01 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 944,762.01 405,952.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 405,952.81