Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 22-069-13-19 10-1N7104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 10-MER-99-R1.1/R1.1 NONE Progress payment No. 002 Payment period ending: 02-24-22 PAVEMENT PRESERVATION SPECIALTIES INC 27801 HALE CT TEHACHAPI CA 93561 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 308,254.72 26,947.92 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 308,254.72 26,947.92 5. Mobilization 6. Total Work Completed 308,254.72 7. Deductions -20,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 288,254.72 6,947.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,947.92