Dept. of Trans. PROGRESS Serial No. Contract No. 24-144-11-09 10-1N7604 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 25% Location: Federal Project: 10-SJ-4-R16.2 NONE Progress payment No. 002 Payment period ending: 05-20-24 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 599,878.50 474,632.25 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 599,878.50 474,632.25 5. Mobilization 85,000.00 21,250.00 6. Total Work Completed 684,878.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 684,878.50 495,882.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 495,882.25