Dept. of Trans. PROGRESS Serial No. Contract No. 21-328-15-02 10-1N8804 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 36% Location: Federal Project: 10-AMA-88-69.0/70.0 NONE Progress payment No. 001 Payment period ending: 11-20-21 MOUNTAIN PRIDE CONSTRUCTION INC PO BOX 620 TAHOE CITY CA 96145 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 450,000.00 450,000.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 450,000.00 450,000.00 5. Mobilization 6. Total Work Completed 450,000.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 450,000.00 450,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 450,000.00