Dept. of Trans. PROGRESS Serial No. Contract No. 24-144-12-58 10-1P7104 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 7% Location: Federal Project: 10-VAR NONE Progress payment No. 001 Payment period ending: 05-20-24 MCCUEN CONSTRUCTION INC 3269 SWETZER RD LOOMIS CA 95650 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 161,692.46 161,692.46 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 958,014.09 958,014.09 4. Earned Subject to Retention 1,119,706.55 1,119,706.55 5. Mobilization 327,462.15 327,462.15 6. Total Work Completed 489,154.61 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,447,168.70 1,447,168.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,447,168.70