Dept. of Trans. PROGRESS Serial No. Contract No. 25-295-14-11 10-1R7204 PROGRESS PAYMENT VOUCHER %complete: %time: 28% 65% Location: Federal Project: 10-VAR NONE Progress payment No. 003 Payment period ending: 10-20-25 MCCUEN CONSTRUCTION INC 3269 SWETZER RD LOOMIS CA 95650 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 569,055.66 350,139.46 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 241,499.31 -50,793.94 4. Earned Subject to Retention 810,554.97 299,345.52 5. Mobilization 246,050.00 51,800.00 6. Total Work Completed 815,105.66 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,056,604.97 351,145.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 351,145.52