Dept. of Trans. PROGRESS Serial No. Contract No. 24-127-15-38 10-1R8904 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 100% Location: Federal Project: 10-ALP-4-3.0/12.5 NONE Progress payment No. 004 Payment period ending: 05-06-24 APEX FENCE CO INC PO BOX 545 ANDERSON CA 96007 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 405,358.02 227,857.18 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 405,358.02 227,857.18 5. Mobilization 6. Total Work Completed 405,358.02 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -27,488.09 -22,785.72 c. Reduction after 95% Comp. 9. Total pay to Contractor 377,869.93 205,071.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 205,071.46