Dept. of Trans. PROGRESS Serial No. Contract No. 24-144-11-49 10-1R9104 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 73% Location: Federal Project: 10-AMA-88-68.0/69.0 NONE Progress payment No. 002 Payment period ending: 05-20-24 TOM MAYO CONSTRUCTION INC 4735 EAST FREMONT ST STOCKTON CA 952154011 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 420,814.65 45,814.65 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 420,814.65 45,814.65 5. Mobilization 6. Total Work Completed 420,814.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 420,814.65 45,814.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 45,814.65