Dept. of Trans. PROGRESS Serial No. Contract No. 25-125-13-52 10-1S4904 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 27% Location: Federal Project: 10-STA-99-17.0/17.0 NONE 10-MER-152-21.2/21.2 Progress payment No. 003 Payment period ending: 04-20-25 SYNERGY CONSTRUCTION & DEVELOPMENT CORP 5109 POMERADO WAY BAKERSFIELD CA 93313 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 798,131.63 290,980.99 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 798,131.63 290,980.99 5. Mobilization 6. Total Work Completed 798,131.63 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 798,131.63 290,980.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 290,980.99