Dept. of Trans. PROGRESS Serial No. Contract No. 24-327-11-50 10-1T4304 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 100% Location: Federal Project: 10-STA-5-229.0/22.9 NONE Progress payment No. 001 Payment period ending: 11-20-24 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 465,836.21 465,836.21 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 465,836.21 465,836.21 5. Mobilization 6. Total Work Completed 465,836.21 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -46,583.62 -46,583.62 c. Reduction after 95% Comp. 9. Total pay to Contractor 419,252.59 419,252.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 419,252.59