Dept. of Trans. PROGRESS Serial No. Contract No. 14-111-10-25 10-264444 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 72% 10-AMA-88-0.0/5.5 Federal Project: ACNH-P088(58) Progress payment No. 27 Payment period ending: 04-20-14 GEORGE REED INC - MYERS AND SONS CONSTRUCTION LP JV P O BOX 4760 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,627,746.99 19,700.00 2.a. Extra Work 702,871.07 0.00 b. Adjustment Comp. 40,512.89 0.00 3. Materials on Hand 4. Earned Subject to Retention 10,371,130.95 19,700.00 5. Mobilization 522,000.00 0.00 6. Total Work Completed 10,893,130.95 7. Deductions -2,500.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,890,630.95 19,700.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,700.00