Dept. of Trans. SEMI-FINAL Serial No. Contract No. 14-269-08-33 10-264444 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-AMA-88-0.0/5.5 Federal Project: ACNH-P088(58) Progress payment No. 32 Payment period ending: 04-30-14 GEORGE REED INC - MYERS AND SONS CONSTRUCTION LP JV P O BOX 4760 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,057,083.49 0.00 2.a. Extra Work 1,043,750.55 130,125.80 b. Adjustment Comp. 58,626.82 -32,537.10 3. Materials on Hand 4. Earned Subject to Retention 11,159,460.86 97,588.70 5. Mobilization 522,000.00 0.00 6. Total Work Completed 11,681,460.86 7. Deductions -2,500.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,678,960.86 97,588.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 97,588.70