Dept. of Trans. SEMI-FINAL Serial No. Contract No. 12-095-09-25 10-279804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-MER-165-11.7/26.7 Federal Project: SARR-STP(11) ASTP-BRST(11) Progress payment No. 08 Payment period ending: 03-07-12 TEICHERT CORPORATION P O BOX 1118 STOCKTON CA 95201 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,532,613.31 5,000.00 2.a. Extra Work 1,043,983.03 19,409.63 b. Adjustment Comp. -29,555.23 75,920.98 3. Materials on Hand 4. Earned Subject to Retention 10,547,041.11 100,330.61 5. Mobilization 1,094,500.00 0.00 6. Total Work Completed 11,641,541.11 7. Deductions -70,000.00 16,670.02 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,571,541.11 117,000.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 117,000.63