Dept. of Trans. PROGRESS Serial No. Contract No. 05-113-10-41 10-281204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 5% 0% 10-STA-120-4.2/6.1 Federal Project: 10-STA-108-37.2/38.2 ACNH-X099(468) Progress payment No. 02 Payment period ending: 04-20-05 GEORGE REED INC P O BOX 4760 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 194,136.40 160,903.30 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 38,589.11 38,589.11 4. Earned Subject to Retention 232,725.51 199,492.41 5. Mobilization 37,500.00 37,500.00 6. Total Work Completed 231,636.40 7. Deductions -16,840.33 -16,090.33 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 253,385.18 220,902.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 220,902.08