Dept. of Trans. PROGRESS Serial No. Contract No. 05-326-13-57 10-281204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 91% 10-STA-120-4.2/6.1 Federal Project: 10-STA-108-37.2/38.2 ACNH-X099(468) Progress payment No. 09 Payment period ending: 11-20-05 GEORGE REED INC P O BOX 4760 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,894,362.83 669,725.25 2.a. Extra Work 153,093.15 -823.68 b. Adjustment Comp. 1,143,653.58 -7,959.10 3. Materials on Hand 9,789.21 -9,104.88 4. Earned Subject to Retention 5,200,898.77 651,837.59 5. Mobilization 75,000.00 0.00 6. Total Work Completed 5,266,109.56 7. Deductions -258,696.92 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,017,201.85 641,837.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 641,837.59