Dept. of Trans. PROGRESS Serial No. Contract No. 06-081-10-34 10-281204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 98% 10-STA-120-4.2/6.1 Federal Project: 10-STA-108-37.2/38.2 ACNH-X099(468) Progress payment No. 13 Payment period ending: 03-20-06 GEORGE REED INC P O BOX 4760 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,345,475.32 19,436.30 2.a. Extra Work 193,471.14 29,274.78 b. Adjustment Comp. 1,244,274.23 -6,417.98 3. Materials on Hand 150,700.28 139,180.29 4. Earned Subject to Retention 5,933,920.97 181,473.39 5. Mobilization 75,000.00 0.00 6. Total Work Completed 5,858,220.69 7. Deductions -49,191.15 -1,943.63 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,959,729.82 179,529.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 179,529.76