Dept. of Trans. FINAL Serial No. Contract No. 11-249-10-53 10-283204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-SJ-4-R8.1/T14.3 Federal Project: ACST-P004(132) P-P004(132) Progress payment No. 03 Payment period ending: 09-14-10 TOP GRADE CONSTRUCTION INC 50 CONTRACTORS STREET LIVERMORE, CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work b. Adjustment Comp. 711,846.07 598,254.50 3. Materials on Hand 4. Earned Subject to Retention 711,846.07 598,254.50 5. Mobilization 6. Total Work Completed 711,846.07 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 711,846.07 598,254.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 598,254.50