Dept. of Trans. PROGRESS Serial No. Contract No. 03-055-10-50 10-2A50U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 15% 10-MER-99-R28.2/R36.4 Federal Project: ACNH-P099(436) Progress payment No. 08 Payment period ending: 02-20-03 J S BRAR COMPANY 7202 E BULLARD AVENUE CLOVIS CA 936119202 Escrow No. 01954 Total Estimate This Estimate 1. Contract Itms Without Mobil. 731,139.51 152,013.69 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -4,882.73 4. Earned Subject to Retention 731,139.51 147,130.96 5. Mobilization 50,673.00 0.00 6. Total Work Completed 781,812.51 7. Deductions 8. a.Contract Retentions -47,872.38 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 733,940.13 147,130.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 147,130.96