Dept. of Trans. PROGRESS Serial No. Contract No. 03-080-13-22 10-2A50U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 17% 10-MER-99-R28.2/R36.4 Federal Project: ACNH-P099(436) Progress payment No. 09 Payment period ending: 03-20-03 J S BRAR COMPANY 7202 E BULLARD AVENUE CLOVIS CA 936119202 Escrow No. 01954 Total Estimate This Estimate 1. Contract Itms Without Mobil. 827,173.10 96,033.59 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 827,173.10 96,033.59 5. Mobilization 50,673.00 0.00 6. Total Work Completed 877,846.10 7. Deductions 8. a.Contract Retentions -47,872.38 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 829,973.72 96,033.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 96,033.59