Dept. of Trans. PROGRESS Serial No. Contract No. 08-296-09-57 10-2A7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 12% 6% 10-STA-99-R11.9/R11.9 Federal Project: NONE Progress payment No. 02 Payment period ending: 10-20-08 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET SUITE G BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,181,292.00 915,151.70 2.a. Extra Work 15,135.82 4,417.69 b. Adjustment Comp. 3. Materials on Hand 193,490.69 -138,000.00 4. Earned Subject to Retention 1,389,918.51 781,569.39 5. Mobilization 820,000.00 820,000.00 6. Total Work Completed 2,016,427.82 7. Deductions 8. a.Contract Retentions -138,991.85 -78,156.94 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,070,926.66 1,523,412.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,523,412.45