Dept. of Trans. PROGRESS Serial No. Contract No. 08-329-11-04 10-2A7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 17% 9% 10-STA-99-R11.9/R11.9 Federal Project: NONE Progress payment No. 03 Payment period ending: 11-20-08 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET SUITE G BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,549,985.50 368,693.50 2.a. Extra Work 25,649.26 10,513.44 b. Adjustment Comp. 3. Materials on Hand 168,833.71 -24,656.98 4. Earned Subject to Retention 1,744,468.47 354,549.96 5. Mobilization 1,230,000.00 410,000.00 6. Total Work Completed 2,805,634.76 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -174,446.85 -35,455.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,790,021.62 719,094.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 719,094.96