Dept. of Trans. PROGRESS Serial No. Contract No. 09-020-09-56 10-2A7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 15% 10-STA-99-R11.9/R11.9 Federal Project: NONE Progress payment No. 05 Payment period ending: 01-20-09 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET SUITE G BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,086,836.57 641,716.45 2.a. Extra Work 96,944.08 0.00 b. Adjustment Comp. 3. Materials on Hand 151,000.00 -54,000.00 4. Earned Subject to Retention 3,334,780.65 587,716.45 5. Mobilization 1,558,000.00 328,000.00 6. Total Work Completed 4,741,780.65 7. Deductions 8. a.Contract Retentions -300,601.41 -25,894.99 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,592,179.24 889,821.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 889,821.46