Dept. of Trans. PROGRESS Serial No. Contract No. 09-294-10-18 10-2A7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 39% 10-STA-99-R11.9/R11.9 Federal Project: NONE Progress payment No. 16 Payment period ending: 10-20-09 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET SUITE G BENICIA CA 94510 Escrow No. 02405 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,624,440.64 456,667.72 2.a. Extra Work 465,742.90 0.00 b. Adjustment Comp. 19,607.97 -59,841.87 3. Materials on Hand 250,782.00 0.00 4. Earned Subject to Retention 10,360,573.51 396,825.85 5. Mobilization 1,640,000.00 0.00 6. Total Work Completed 11,749,791.51 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -518,028.68 -19,841.30 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,472,544.83 366,984.55 10. Reduction Amt to Escrow 11. Payment to Escrow 518,020.00 12. Net Pymt. this Estimate 366,984.55