Dept. of Trans. PROGRESS Serial No. Contract No. 11-024-08-26 10-2A7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 83% 10-STA-99-R11.9/R11.9 Federal Project: NONE Progress payment No. 31 Payment period ending: 01-20-11 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET SUITE G BENICIA CA 94510 Escrow No. 02405 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,958,587.21 183,036.40 2.a. Extra Work 708,180.37 46,233.90 b. Adjustment Comp. 16,241.48 -23,500.00 3. Materials on Hand 0.00 -50,000.00 4. Earned Subject to Retention 15,683,009.06 155,770.30 5. Mobilization 1,640,000.00 0.00 6. Total Work Completed 17,323,009.06 7. Deductions -35,000.00 -30,000.00 8. a.Contract Retentions -784,150.45 -7,788.51 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,503,858.61 117,981.79 10. Reduction Amt to Escrow 11. Payment to Escrow 784,150.00 12. Net Pymt. this Estimate 117,981.79