Dept. of Trans. PROGRESS Serial No. Contract No. 11-171-13-55 10-2A7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 95% 10-STA-99-R11.9/R11.9 Federal Project: NONE Progress payment No. 36 Payment period ending: 06-17-11 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET SUITE G BENICIA CA 94510 Escrow No. 02405 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,258,080.10 16,000.00 2.a. Extra Work 911,739.36 86,008.47 b. Adjustment Comp. 32,941.48 0.00 3. Materials on Hand 4. Earned Subject to Retention 16,202,760.94 102,008.47 5. Mobilization 1,640,000.00 0.00 6. Total Work Completed 17,842,760.94 7. Deductions -45,000.00 1,000.00 8. a.Contract Retentions -810,138.05 -5,100.43 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,987,622.89 97,908.04 10. Reduction Amt to Escrow 11. Payment to Escrow 810,130.00 12. Net Pymt. this Estimate 97,908.04