Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 11-189-07-47 10-2A7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-STA-99-R11.9/R11.9 Federal Project: NONE Progress payment No. 37 Payment period ending: 06-27-11 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET SUITE G BENICIA CA 94510 Escrow No. 02405 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,276,134.10 18,054.00 2.a. Extra Work 1,044,433.20 132,693.84 b. Adjustment Comp. -84,325.71 -117,267.19 3. Materials on Hand 4. Earned Subject to Retention 16,236,241.59 33,480.65 5. Mobilization 1,640,000.00 0.00 6. Total Work Completed 17,876,241.59 7. Deductions -16,000.00 29,000.00 8. a.Contract Retentions -810,138.05 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 810,138.05 810,138.05 9. Total pay to Contractor 17,860,241.59 872,618.70 10. Reduction Amt to Escrow -810,130.00 -810,130.00 11. Payment to Escrow 810,130.00 12. Net Pymt. this Estimate 62,488.70