Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-199-10-00 10-2A7704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 10-STA-99-R11.9/R11.9 Federal Project: NONE Progress payment No. 38 Payment period ending: 06-27-11 NEHEMIAH CONSTRUCTION INC 801 FIRST STREET SUITE G BENICIA CA 94510 Escrow No. 02405 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,300,534.10 24,400.00 2.a. Extra Work 1,053,960.60 9,527.40 b. Adjustment Comp. -84,325.71 0.00 3. Materials on Hand 4. Earned Subject to Retention 16,270,168.99 33,927.40 5. Mobilization 1,640,000.00 0.00 6. Total Work Completed 17,910,168.99 7. Deductions -11,000.00 5,000.00 8. a.Contract Retentions -810,138.05 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 810,138.05 0.00 9. Total pay to Contractor 17,899,168.99 38,927.40 10. Reduction Amt to Escrow -810,130.00 0.00 11. Payment to Escrow 810,130.00 12. Net Pymt. this Estimate 38,927.40