Dept. of Trans. PROGRESS Serial No. Contract No. 07-296-08-40 10-300164 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 42% 10-SJ-205-R3.0/R13.6 Federal Project: ACNH-X077(14) I-X077(14) Progress payment No. 19 Payment period ending: 10-20-07 O C JONES C C MYERS A JOINT VENTURE 1520 FOURTH STREET BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,108,835.77 2,751,618.96 2.a. Extra Work 2,150,529.31 151,613.40 b. Adjustment Comp. 1,084,218.19 472,902.52 3. Materials on Hand 380,664.35 -564,000.00 4. Earned Subject to Retention 34,724,247.62 2,812,134.88 5. Mobilization 5,652,500.00 0.00 6. Total Work Completed 39,996,083.27 7. Deductions -112,961.58 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 40,263,786.04 2,802,134.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,802,134.88