Dept. of Trans. PROGRESS Serial No. Contract No. 08-205-07-29 10-300164 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 66% 10-SJ-205-R3.0/R13.6 Federal Project: ACNH-X077(14) I-X077(14) Progress payment No. 30 Payment period ending: 07-20-08 O C JONES C C MYERS A JOINT VENTURE 1520 FOURTH STREET BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 47,283,310.43 1,092,477.89 2.a. Extra Work 5,680,988.14 1,012,920.69 b. Adjustment Comp. 2,432,753.54 409,460.82 3. Materials on Hand 625,682.32 144,739.28 4. Earned Subject to Retention 56,022,734.43 2,659,598.68 5. Mobilization 5,950,000.00 0.00 6. Total Work Completed 61,347,052.11 7. Deductions -49,455.50 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 61,923,278.93 2,659,598.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,659,598.68