Dept. of Trans. PROGRESS Serial No. Contract No. 06-326-10-38 10-3169E4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 55% 37% 10-MER-99-26.5/R28.8 Federal Project: ACNH-P099(487) Progress payment No. 12 Payment period ending: 11-20-06 AGEE CONSTRUCTION CORPORATION P O BOX 629 CLOVIS CA 93613 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,057,307.12 846,342.42 2.a. Extra Work 21,285.47 0.00 b. Adjustment Comp. 63,649.76 0.00 3. Materials on Hand 119,868.46 -3,685.42 4. Earned Subject to Retention 11,262,110.81 842,657.00 5. Mobilization 2,185,000.00 0.00 6. Total Work Completed 13,327,242.35 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,447,110.81 842,657.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 842,657.00