Dept. of Trans. PROGRESS Serial No. Contract No. 07-267-08-37 10-3169E4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 81% 10-MER-99-26.5/R28.8 Federal Project: ACNH-P099(487) Progress payment No. 23 Payment period ending: 09-20-07 AGEE CONSTRUCTION CORPORATION P O BOX 629 CLOVIS CA 93613 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,183,501.33 1,012,864.58 2.a. Extra Work 142,044.11 -111.25 b. Adjustment Comp. 92,532.29 0.00 3. Materials on Hand 33,342.34 0.00 4. Earned Subject to Retention 18,451,420.07 1,012,753.33 5. Mobilization 2,300,000.00 0.00 6. Total Work Completed 20,718,077.73 7. Deductions -13,693.14 -6,950.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,737,726.93 1,005,803.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,005,803.33