Dept. of Trans. PROGRESS Serial No. Contract No. 00-266-14-39 10-351704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 27% 10-ALP-88-4.0/5.2 Federal Project: ACNH-P088(38) Progress payment No. 03 Payment period ending: 09-20-00 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 204,773.31 142,808.30 2.a. Extra Work 24,712.29 24,712.29 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 229,485.60 167,520.59 5. Mobilization 90,000.00 30,000.00 6. Total Work Completed 319,485.60 7. Deductions 8. a.Contract Retentions -22,948.56 -16,752.06 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 296,537.04 180,768.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 180,768.53