Dept. of Trans. PROGRESS Serial No. Contract No. 09-079-12-43 10-362504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 21% 10-CAL-4-R21.1/R23.4 Federal Project: NONE Progress payment No. 14 Payment period ending: 03-20-09 TEICHERT CONSTRUCTION P O BOX 1118 STOCKTON CA 952011118 Escrow No. 02363 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,101,716.40 624,493.00 2.a. Extra Work 633,524.37 109,746.39 b. Adjustment Comp. 43,136.00 0.00 3. Materials on Hand 37,577.00 -81,719.00 4. Earned Subject to Retention 16,815,953.77 652,520.39 5. Mobilization 2,350,000.00 0.00 6. Total Work Completed 19,128,376.77 7. Deductions -10,400.00 0.00 8. a.Contract Retentions -840,797.69 -32,626.02 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 18,314,756.08 619,894.37 10. Reduction Amt to Escrow 11. Payment to Escrow 600,000.00 12. Net Pymt. this Estimate 619,894.37