Dept. of Trans. PROGRESS Serial No. Contract No. 06-324-08-25 10-363114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 37% 10-MER-99-10.2/12.8 Federal Project: ACNH-P099(493) Progress payment No. 13 Payment period ending: 11-20-06 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 45,946,115.12 2,429,885.19 2.a. Extra Work 118,615.05 0.00 b. Adjustment Comp. 59,022.21 0.00 3. Materials on Hand 337,121.77 15,100.64 4. Earned Subject to Retention 46,460,874.15 2,444,985.83 5. Mobilization 6,655,000.50 0.00 6. Total Work Completed 52,778,752.88 7. Deductions -5,513.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 53,110,361.65 2,444,985.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,444,985.83